 CONSTRUCTION OF THE PPDA HEAD OFFICE-PROGRESS
July 12, 2019

PROGRESS OF THE CONSTRUCTION WORK OF THE PPDA HEAD OFFICE

Public Procurement and Disposal of Public Assets Authority (PPDA) and Uganda Road Fund (URF) started construction work of a joint structure to house their Head offices.

The 10 storey twin-tower building is  be located at on Plot Road in Nakasero Kampala, on an expanse of14, 796 square meters.

The construction work is  undertaken by Seyani Brothers Company Limited and Symbion Constructing Group as the supervising consultants.

The Overall progress of the work is currently  at 22%, Lateral support and basements 3, 2, and 1 completed and the Ground Floor at 66%.